POWERGRID acquires Lakadia-II SPV to evacuate Gujarat renewable power

The company took full control of Lakadia II Power Transmission Limited after winning the TBCB bid for a transmission link serving the 7,500 MW Lakadia renewable-energy zone in Gujarat.

What was filed

Power Grid Corporation of India told the exchanges it acquired Lakadia II Power Transmission Limited, a project-specific SPV, on 12 October 2026. The acquisition follows POWERGRID's selection as successful bidder under Tariff Based Competitive Bidding (TBCB), with the SPV transferred on a build, own, operate and transfer (BOOT) basis from the Bid Process Coordinator, REC Power Development and Consultancy Limited (RECPDCL). The SPV was incorporated only on 09 May 2026, has not yet begun commercial operations, and carries no turnover history.

The project

The SPV holds the mandate to build an inter-state transmission system integrating power from renewable projects in the Lakadia renewable-energy zone (REZ) in Gujarat, which the filing links to 7,500 MW of capacity. The scope covers a new 765/400 kV Lakadia-II substation in Gujarat, associated 765 kV transmission lines through the state with related equipment and bays, and the installation and commissioning of a synchronous condenser at the substation. Per the filing, transmission licence and tariff-adoption approvals are still to be obtained from the Central Electricity Regulatory Commission after the acquisition.

Terms and what they mean for a holder

The transaction is for cash, giving POWERGRID full control of an entity in its core line of business — power transmission. The filing notes the acquisition price is subject to adjustment against the SPV's audited accounts as on the acquisition date. This adds another competitively-won asset to POWERGRID's regulated transmission pipeline, but the SPV is pre-operational, so any revenue would depend on construction, commissioning and the pending regulatory approvals described in the filing.

Shareholding / control acquired
100%
Equity shares acquired
50,000 equity shares at par at Rs. 10/- each
RE zone capacity referenced
7500 MW

The acquisition adds another TBCB-won transmission asset to POWERGRID's portfolio, but the SPV is newly incorporated and pre-revenue, and licence and tariff approvals from CERC are still pending per the filing — so any earnings contribution depends on later construction and regulatory steps.

Share this

The brief

You just read one filing on Power Grid Corporation of India. We do this every morning — for the stocks you own.

A calm, cited reading of your own holdings, delivered daily on Telegram or email. No tips.

Free during the pilot.

Read all articles